Monday, 1 February 2016

PRINCIPLES,Control,Economy of accuracy in surveying


1.2 PRINCIPLES
Every profession must be founded upon sound practice and in this engineering surveying is no different.
Practice in turn must be based upon proven principles. This section is concerned with examining the
principles of survey, describing their interrelationship and showing how they may be applied in practice.
Most of the principles below have an application at all stages of a survey and it is an unwise and
unprofessional surveyor who does not take them into consideration when planning, executing, computing
and presenting the results of the survey work. The principles described here have application across the
whole spectrum of survey activity, from field work to photogrammetry, mining surveying to metrology,
hydrography to cartography, and cadastral to construction surveying.
1.2.1 Control
A control network is the framework of survey stations whose coordinates have been precisely determined
and are often considered definitive. The stations are the reference monuments, to which other survey work
of a lesser quality is related. By its nature, a control survey needs to be precise, complete and reliable and
it must be possible to show that these qualities have been achieved. This is done by using equipment of
proven precision, with methods that satisfy the principles and data processing that not only computes the
correct values but gives numerical measures of their precision and reliability.
Since care needs to be taken over the provision of control, then it must be planned to ensure that it
achieves the numerically stated objectives of precision and reliability. It must also be complete as it will
be needed for all related and dependent survey work. Other survey works that may use the control will
usually be less precise but of greater quantity. Examples are setting out for earthworks on a construction
site, detail surveys of a greenfield site or of an as-built development and monitoring many points on a
structure suspected of undergoing deformation.
The practice of using a control framework as a basis for further survey operations is often called ‘working
from the whole to the part’. If it becomes necessary to work outside the control framework then it must
be extended to cover the increased area of operations. Failure to do so will degrade the accuracy of later
survey work even if the quality of survey observations is maintained.
For operations other than setting out, it is not strictly necessary to observe the control before other
survey work. The observations may be concurrent or even consecutive. However, the control survey must
be fully computed before any other work is made to depend upon it.
1.2.2 Economy of accuracy
Surveys are only ever undertaken for a specific purpose and so should be as accurate as they need to be, but
not more accurate. In spite of modern equipment, automated systems, and statistical data processing the
business of survey is still a manpower intensive one and needs to be kept to an economic minimum. Once
the requirement for a survey or some setting out exists, then part of the specification for the work must
include a statement of the relative and absolute accuracies to be achieved. From this, a specification for
the control survey may be derived and once this specification has been achieved, there is no requirement
for further work.
Whereas control involves working from ‘the whole to the part’ the specification for all survey products
is achieved by working from ‘the part to the whole’. The specification for the control may be derived from
estimation based upon experience using knowledge of survey methods to be applied, the instruments to
be used and the capabilities of the personnel involved. Such a specification defines the expected quality of
the output by defining the quality of the work that goes into the survey. Alternatively a statistical analysis
of the proposed control network may be used and this is the preferable approach. In practice a good
specification will involve a combination of both methods, statistics tempered by experience. The accuracy
 written down in the field must be in a permanent, legible, unambiguous and easily understood form so that
others may make good sense of the work. Observations and other data should be duplicated at the earliest
possible stage, so that if something happens to the original work the information is not lost. This may be
by photocopying field sheets, or making backup copies of computer files. Whenever the data is in a unique
form or where all forms of the data are held in the same place, then that data is vulnerable to accidental
destruction.
In the case of a control survey, the protection of survey monuments is most important since the precise
coordinates of a point which no longer exists or cannot be found are useless


No comments:

Post a Comment