Monday, 1 February 2016

BASIC MEASUREMENTS,SURVEYING

                             Surveying is concerned with the fixing of position whether it be control points or points of topographic
detail and, as such, requires some form of reference system.
The physical surface of the Earth, on which the actual survey measurements are carried out, is not
mathematically definable. It cannot therefore be used as a reference datum on which to compute position.
Alternatively, consider a level surface at all points normal to the direction of gravity. Such a surface
would be closed and could be formed to fit the mean position of the oceans, assuming them to be free from
all external forces, such as tides, currents, winds, etc. This surface is called the geoid and is defined as the
equipotential surface that most closely approximates to mean sea level in the open oceans.An equipotential
surface is one from which it would require the same amount of work to move a given mass to infinity no
matter from which point on the surface one started. Equipotential surfaces are surfaces of equal potential;
they are not surfaces of equal gravity. The most significant aspect of an equipotential surface going through
an observer is that survey instruments are set up relative to it. That is, their vertical axes are in the direction
of the force of gravity at that point. A level or equipotential surface through a point is normal, i.e. at right
angles, to the direction of gravity. Indeed, the points surveyed on the physical surface of the Earth are
frequently reduced, initially, to their equivalent position on the geoid by projection along their gravity
vectors.
The reduced level or elevation of a point is its height above or below the geoid as measured in the
direction of its gravity vector, or plumb line, and is most commonly referred to as its height above or below
mean sea level (MSL). This assumes that the geoid passes through local MSL, which is acceptable for most
practical purposes. However, due to variations in the mass distribution within the Earth, the geoid, which
although very smooth is still an irregular surface and so cannot be used to locate position mathematically.
The simplest mathematically definable figure which fits the shape of the geoid best is an ellipsoid formed
by rotating an ellipse about its minor axis. Where this shape is used by a country as the surface for its
mapping system, it is termed the reference ellipsoid. Figure 1.1 illustrates the relationship between these
surfaces.
The majority of engineering surveys are carried out in areas of limited extent, in which case the reference
surface may be taken as a tangent plane to the geoid and the principles of plane surveying applied. In other
words, the curvature of the Earth is ignored and all points on the physical surface are orthogonally projected
onto a flat plane as illustrated in Figure 1.2. For areas less than 10 km square the assumption of a flat Earth is
perfectly acceptable when one considers that in a triangle of approximately 200km2, the difference between
the sum of the spherical angles and the plane angles would be 1 second of arc, or that the difference in length
of an arc of approximately 20 km on the Earth’s surface and its equivalent chord length is a mere 8 mm.
The above assumptions of a flat Earth, while acceptable for some positional applications, are not
acceptable for finding elevations, as the geoid deviates from the tangent plane by about 80 mm at 1 km or
8 m at 10 km from the point of contact. Elevations are therefore referred to the geoid, at least theoretically,
but usually to MSL practically.
to several kilometres with millimetre precision, depending on the distance measured; lasers and northseeking
gyroscopes are virtually standard equipment for tunnel surveys; orbiting satellites are being used
for position fixing offshore as well as on; continued improvement in aerial and terrestrial photogrammetric
and scanning equipment makes mass data capture technology an invaluable surveying tool; finally, data
loggers and computers enable the most sophisticated procedures to be adopted in the processing and
automatic plotting of field data.

PRINCIPLES,Control,Economy of accuracy in surveying


1.2 PRINCIPLES
Every profession must be founded upon sound practice and in this engineering surveying is no different.
Practice in turn must be based upon proven principles. This section is concerned with examining the
principles of survey, describing their interrelationship and showing how they may be applied in practice.
Most of the principles below have an application at all stages of a survey and it is an unwise and
unprofessional surveyor who does not take them into consideration when planning, executing, computing
and presenting the results of the survey work. The principles described here have application across the
whole spectrum of survey activity, from field work to photogrammetry, mining surveying to metrology,
hydrography to cartography, and cadastral to construction surveying.
1.2.1 Control
A control network is the framework of survey stations whose coordinates have been precisely determined
and are often considered definitive. The stations are the reference monuments, to which other survey work
of a lesser quality is related. By its nature, a control survey needs to be precise, complete and reliable and
it must be possible to show that these qualities have been achieved. This is done by using equipment of
proven precision, with methods that satisfy the principles and data processing that not only computes the
correct values but gives numerical measures of their precision and reliability.
Since care needs to be taken over the provision of control, then it must be planned to ensure that it
achieves the numerically stated objectives of precision and reliability. It must also be complete as it will
be needed for all related and dependent survey work. Other survey works that may use the control will
usually be less precise but of greater quantity. Examples are setting out for earthworks on a construction
site, detail surveys of a greenfield site or of an as-built development and monitoring many points on a
structure suspected of undergoing deformation.
The practice of using a control framework as a basis for further survey operations is often called ‘working
from the whole to the part’. If it becomes necessary to work outside the control framework then it must
be extended to cover the increased area of operations. Failure to do so will degrade the accuracy of later
survey work even if the quality of survey observations is maintained.
For operations other than setting out, it is not strictly necessary to observe the control before other
survey work. The observations may be concurrent or even consecutive. However, the control survey must
be fully computed before any other work is made to depend upon it.
1.2.2 Economy of accuracy
Surveys are only ever undertaken for a specific purpose and so should be as accurate as they need to be, but
not more accurate. In spite of modern equipment, automated systems, and statistical data processing the
business of survey is still a manpower intensive one and needs to be kept to an economic minimum. Once
the requirement for a survey or some setting out exists, then part of the specification for the work must
include a statement of the relative and absolute accuracies to be achieved. From this, a specification for
the control survey may be derived and once this specification has been achieved, there is no requirement
for further work.
Whereas control involves working from ‘the whole to the part’ the specification for all survey products
is achieved by working from ‘the part to the whole’. The specification for the control may be derived from
estimation based upon experience using knowledge of survey methods to be applied, the instruments to
be used and the capabilities of the personnel involved. Such a specification defines the expected quality of
the output by defining the quality of the work that goes into the survey. Alternatively a statistical analysis
of the proposed control network may be used and this is the preferable approach. In practice a good
specification will involve a combination of both methods, statistics tempered by experience. The accuracy
 written down in the field must be in a permanent, legible, unambiguous and easily understood form so that
others may make good sense of the work. Observations and other data should be duplicated at the earliest
possible stage, so that if something happens to the original work the information is not lost. This may be
by photocopying field sheets, or making backup copies of computer files. Whenever the data is in a unique
form or where all forms of the data are held in the same place, then that data is vulnerable to accidental
destruction.
In the case of a control survey, the protection of survey monuments is most important since the precise
coordinates of a point which no longer exists or cannot be found are useless


Basic concepts of surveying

 Basic concepts of surveying

1.1 DEFINITION
Surveying may be defined as the science of determining the position, in three dimensions, of natural andman-made features on or beneath the surface of the Earth. These features may be represented in analogueform as a contoured map, plan or chart, or in digital form such as a digital ground model (DGM).
In engineering surveying, either or both of the above formats may be used for planning, design andconstruction of works, both on the surface and underground. At a later stage, surveying techniques areused for dimensional control or setting out of designed constructional elements and also for monitoringdeformation movements.In the first instance, surveying requires management and decision making in deciding the appropriatemethods and instrumentation required to complete the task satisfactorily to the specified accuracy andwithin the time limits available. This initial process can only be properly executed after very careful anddetailed reconnaissance of the area to be surveyed.When the above logistics are complete, the field work – involving the capture and storage of field data –is carried out using instruments and techniques appropriate to the task in hand.Processing the data is the next step in the operation. The majority, if not all, of the computation willbe carried out with computing aids ranging from pocket calculator to personal computer. The methodsadopted will depend upon the size and precision of the survey and the manner of its recording; whetherin a field book or a data logger. Data representation in analogue or digital form may now be carried outby conventional cartographic plotting or through a totally automated computer-based system leading toa paper- or screen-based plot. In engineering, the plan or DGM is used when planning and designing aconstruction project. The project may be a railway, highway, dam, bridge, or even a new town complex.No matter what the work is, or how complicated, it must be set out on the ground in its correct place and to itscorrect dimensions, within the tolerances specified. To this end, surveying procedures and instrumentationof varying precision and complexity are used depending on the project in hand.Surveying is indispensable to the engineer when planning, designing and constructing a project, soall engineers should have a thorough understanding of the limits of accuracy possible in the constructionand manufacturing processes. This knowledge, combined with an equal understanding of the limits andcapabilities of surveying instrumentation and techniques, will enable the engineer to complete the projectsuccessfully in the most economical manner and in the shortest possible time.